Photo Galleries
 
Click on photo to see gallery.

September 11, 2007

Tear down of existing Hardee's building begins.
click to see gallery
October 8, 2007
Outside structure is all that remains standing of existing Hardee's building.
click to see gallery
October 25, 2007
Teardown of the existing Hardee's structure completed.
click to see gallery
November 5, 2007
Volunteer Fire Fighters and City Members break ground for new fire station.
click to see gallery
March 17, 2008
Concrete is broken up and prepared for recycling.
click to see gallery
March 19, 2008
Concrete is removed and piled for recycling.
click to see gallery
March 26, 2008
Recycling of concrete begins.
click to see gallery
March 28, 2008
Dirt moving begins as concrete is completely ground and piled for later use.
click to see gallery
April 1, 2008
Leveling of site begins, as utilities begin to be installed.
click to see gallery
April 2, 2008
Utilities are being installed.
click to see gallery
April 3, 2008
Footings for building begin to be dug.
click to see gallery
April 8, 2008
Footing forms are erected in the trenches where the footings are to be poured.
click to see gallery
April 12, 2008
More footing forms are installed.
click to see gallery
April 15, 2008
Footing cement poured for part of the footings.
April 16, 2008
Drainage installed.
April 21, 2008
Foundation forms go up, building steel arrives.
April 23, 2008
Foundation forms continue to be installed.
April 25, 2008
Part of foundation is poured.
April 28, 2008
More of the foundation forms are installed
April 30, 2008
Second foundation pour is completed.
May 2, 2008
Foundation nears completion, rain setting back crews.
May 7, 2008
Foundation for partition wall between office area and bays being set.
May 9, 2008
Foundation for partition wall between office area and bays poured, and last section of foundation is formed.
May 12, 2008
Apparatus bay sidewall steel starting to be put in place.
May 14, 2008
Completion of the apparatus bay sidewall steel and starting roof supports.
May 16, 2008
Roof supports near completion.
May 20, 2008

Wall panels start to be put in place.

May 22, 2008

More wall panels installed.

May 28, 2008
Partition wall between apparatus bay and office area begins.
May 30, 2008
Partition wall between apparatus bay and office area nears completion.

June 3, 2008

Roof goes on office area
June 5, 2008

Electrical box foundation poured, canopy footings poured

June 10, 2008

Office roof work continues

June 12, 2008 Canopy foundations are poured, mezzanine footings are poured
June 16, 2008 In floor heat tubing is installed in office area, and beginning in bay area
June 19, 2008 In floor heat continues to be installed in offices and bay area
June 24, 2008 Mezzanine beams are delivered and roof steel is beginning to be installed
June 26, 2008 Office enclosed and floor conrete is poured
July 5, 2008 Mezzanine steel is set, and office wall studs are installed

July 10, 2008

In floor heat in bays continues, utilities in office area begin to be installed in walls
July 14, 2008 In floor heat in bays nears completion and exterior sheeting on upper bay walls is installed
July 24, 2008 Concrete floor is poured in bay area, and sheetrock begins in office area
August 12, 2008 Office completely closed in and drywall seam taping begins, work on mezzanine floor begins
August 20, 2008 Office windows are installed, mezzanine floor complete and mezzanine walls begin
September 3, 2008 Front entry door installed, bay doors installed, and retaining wall to north edge of property is completed
September 21, 2008 Concrete driveways and sidewalks are poured, interior painting and finish work begins
October 26, 2008 Interior finish work nears completion, furniture and other interior items installed and delivered
November 1, 2008 Moving day finally arrives